Our team information can be found at the following link Facilities & Project Team

 

SMT have recognised the issues staff are having regarding the heating problems within the Main library and are working with the Library Facilities and Projects team to press Campus Infrastructure and Operations for a swift resolution. It is expected that the temporary heating solution will  be operational throughout the building by the end of the week.

 

1st floor main library:

 

Temporary heating will be provided by means of 2.8kw electric heaters.  We are still in the process of installing supplementary power to all areas that will enable us to fully deploy these heaters. Survey work is being undertaken tonight and tomorrow, with the intention of installing 2 X 60-amp supplementary power circuits: one for either end of the library. Works are expected to be complete by the end of this week. In the meantime, we have plugged in as many lower powered heaters as possible to mitigate the cold temps.

 

2nd floor

 

The 2nd floor temp heating solution will be provided by means of 20 stand only A/C split units, that will be secured in the window bays. These units only take a small amount of energy compared to the 2.8kw heaters. We also have supplementary power on the roof that we will use to feed these units. Works expected to be complete by the end of this week.

 

If you experience any concerns during the duration of this project, please do contact the Facilities and Projects team on: lib-facilities@ucl.ac.uk