Library Facilities and Projects Team Blog: Summer works update

By Collette E M Lawrence, on 31 July 2019

There will be several projects being carried out during this summer, the details are below, if you have any queries please do not hesitate to contact the Facilities and Projects team james.woodhouse@ucl.ac.uk, phil.watson@ucl.ac.uk or c.lawrence@ucl.ac.uk:

Senate House Hub : Work to refurbish the Senate House Hub will be starting on 12th August 2019. During this time Senate House Hub will be closed, the work will take about 4 weeks to complete and will be re-opening in early September 2019. When the space re-opens it will be a dedicated Post Graduate Research (PGR) and Centre for Doctorial Training (CDT) space. There will be new training room fitted, an increase of study spaces and additional comfortable study spaces.

Graduate Hub: Work will be starting on 12th August 2019 , the work will take about 4 weeks to complete, during this time this space will be closed for the duration of the works, and re-opening early September 2019. This is work is taking place to increase the number of study spaces, have more study focused furniture and a refurbished kitchen and main study rooms.

IOE Entrance:Work is taking place with effect from 12th August 2019, users of the Library will be redirected by additional signage and assistance from Library staff and Security. The project will install new turnstiles with accessible lanes in and out, a new single combined service desk with Library and ISD in one place, Smart Shelves return system and a new self-issue kiosk. This work is due to be completed by early September 2019.

Changing Places Accessibility Toilet – Science Library: work for this will be starting on the 12th August 2019. This will create the first nationally listed Changing Places Toilet at UCL.  The work will take about 7 weeks to complete.

Electrical Infrastructure on Central Campus: Noisy works will be associated with the drilling etc. with installation of cabling containment.  We are not expecting this to generate any vibration issues.

The works are the replacement of the two Transformers associated with the T2 Substation, located at the Ground floor level of Petrie Museum.  All works will be confined to within the substation rooms, but will generate noise during the working week, and will – on the weekend of Transformer delivery – impact the Malet Place road way usage.

Outline programme:

  • 22nd July – 2nd August – Cable / Containment and associated builders works:
  • 3rd/4th August – Transformer # 1 replacement (Load management)
  • 5th August – 6th September – Remaining preparation / modification works:
  • 7th/8th September – Transformer # 2 replacement
  • 9th – 13th September – Final snagging and making good.
  • 13th September – Work completed

Science Library Windows: There will be contractors surveying the windows at various times throughout the Science Library, this is in preparation for work to start in the summer of 2020 to replace them.